• Client: NDFA
  • Architect: Healy & Partners Architects
  • Duration: March 2014 - September 2015
  • Contract value: £6.6m
Download Case Study

Under NDFA Design & Build Framework Agreement, JJ Rhatigan & Company won the contract for Bundles 1 and 3 schools which involved the design and build of primary and post primary schools on 10 different sites comprising a mix of new build, replacement, refurbishment and extension.

Presentation Secondary School was part of Bundle 3 Schools and comprised of the construction of a new two storey secondary school on a site immediately adjacent to an existing school. The new school is organised in two main wings with a central link open plan area and a large PE Hall projecting from one wing. The school consists of the following:

  • 24 General Classrooms
  • 3 Science Labs
  • 2 Computer Labs
  • 2 Construction Studies Rooms
  • Art Room
  • Design & Graphics
  • Home Economics Room
  • Engineering Room
  • A Multi-Media Lab
  • A Staff Room
  • All associated offices, stores and toilets.

The existing school was kept fully operational at all times.  During the works, some of the temporary classrooms needed to be relocated to allow site works to be progressed.