Na Blatha Creige, Clybaun Rd., Galway
| Client: Galway CityCouncil |
| Architect: Galway City Council |
| Quantity Surveyor: Davis Langdon PKS |
| Contract Duration: January '06 to August '07 |
| Contract Value:
10,000,000 |
|
|
 |
| |
|
|
 |
| |
|
|
|
Castle Way Apartments, Dublin
| Client: Rhatigan Developments Ltd. (sister company of J J Rhatigan & Co.) |
| Architect: Anthony Reddy Associates |
| Quantity Surveyor: In House (J J Rhatigan & Co.) |
| Contract Duration: September '04 to September '06 |
| Contract Value:
20,000,000 |
|
|
 |
| |
|
|
 |
| |
|
|
|
Mixed Development, Athenry, Galway
| Architect: Atlantic Architects |
| Quantity Surveyor: O'Kelly Partnership |
| Contract Duration: November 04 - October 05 |
| Contract Value:
12,000,000 |
|
|
 |
| |
|
|
 |
| |
|
|
|
Retail/Residential Development at Bridge House, Spiddal, Co. Galway
| Quantity Surveyor: Peter F Costello & Partners |
| Contract Duration: May 04 - Feb 05 |
|
|
 |
| |
|
|
 |
| |
|
|
|
Apartment Development for Cluid Housing, Clifden
| Client: Cluid Housing Association |
| Architect: O'Riain & Associates |
| Quantity Surveyor: Noel J Farrell & Associates |
| Contract Duration: Nov 02 - June 04 |
| Contract Value:
6,000,000 |
|
|
 |
| |
|
|
 |
| |
|
|
|
Kirwan's Lane, Galway Commercial/Residential/Retail Development
| Client: Cross Developments Limited |
| Architect: Douglas Wallace Architects, Dublin |
| Quantity Surveyor: In House |
| Structural Engineer: Hugh Griffin & Associates, Galway |
| Service Engineer:
Heavey Kenny & Partners, Galway |
| Contract Duration: 16 months |
| Contract Value:
5,400,000 euro |
|
|
 |
| |
|
|
 |
| |
|
|
|
Office Development, Ship Street, Dublin
| Client: Luxor Developments Limited |
| Architect: Anthony Reddy & Associates |
| Quantity Surveyor: In House |
| Structural Engineer: Michael Punch & Partners |
| Contract Duration: 17 months, Jan 02 Jun 03 |
| Contract Value:
5,000,000 euro |
|
|
 |
| |
|
|
 |
| |
|
|
|
Millers Apartment Development, Clifden
| Client: The Sweeney Group |
| Architect: Access Building Design |
| Quantity Surveyor: Noel J Farrell & Associates |
| Structural Engineer: Hugh Griffin & Associates |
| Contract Duration: 9 months, Jul 02 Apr 03 |
| Contract Value:
2,900,000 euro |
|
|
 |
| |
|
|
 |
| |
|
|
|
Cluid Housing Development, Tuam
| Client: Cluid Housing Association |
| Architect: ORiain & Associates |
| Quantity Surveyor: Noel J Farrell & Associates |
| Structural Engineer: Hugh Griffin & Associates |
| Contract Duration: 12 months, Nov 02 Dec 03 |
| Contract Value:
9,000,000 euro |
|
|
 |
| |
|
|
 |
| |
|
|
|